-
Performance of Substantiation of RAW Safety Storage at Sites during Operation of Power Units at Above-Design Lifetime
Period: 2009 Customer : SS South Ukrainian NPP / SE NNEGC “Energoatom” Contents of the necessary services during project execution: collection, study and analysis of design documentation; carrying out of...
-
Revision of the Effective Instructions
Period: 2008 Customer: SS “Khmelnitsky NPP”, SS “Rivne NPP” Beneficiary: State Enterprise NNEGC “EnergoAtom” The task order includes the following scope of activities: 1. Revision of the effective instructions on...
-
Development of Radiation Survey Programs for Rivne NPP Units 1,2
Period: 2008 Customer: State Enterprise NNEGC “EnergoAtom” SS “Rivne NPP” The project objective is development, technical support and agreement of the following documents: “Programs for Radiation Survey of Equipment, Pipelines...
-
Development of Requirements for Structure and Contents of Radiation Protection Program and Environmental Monitoring During NPP Power Unit Decommissioning
Period: 2008 Customer: SS “Scientific and Technical Center” State Enterprise NNEGC “EnergoAtom”, NPPs of Ukraine The project objective is realization of the state policy on ensuring radiation security during NPP...
-
Development of Task Order for VVER-440 Units Decommissioning Project
Period: 2008-2009 Customer: SS “Scientific and Technical Center” Beneficiary: State Enterprise NNEGC “EnergoAtom”, SS Rivne NPP The project objective is development of a detailed task order (TO) for a VVER-440...
-
Project of Khmelnitsky NPP Unit 1 In-Depth Safety Assessment: Probabilistic Safety Analysis (PSA) of Internal Initiators – Phases 2&3
Period: 2006-2007 Customer: Pacific Northwest National Laboratory (PNNL), USA Beneficiary: SS Khmelnitsky NPP The following activities were performed within the project framework: final collection and correction of databases on the...